We’re finally seeing Studio Gang’s creative design coming together at Spelman College’s Center for Innovation & The Arts. Following closely behind Turner Construction’s crews, we have completed our solar shades and corrugated Morin panels on one elevation and started the Morin on a second. We have also started installing ACM on the first elevation and […]
We’re finally seeing Studio Gang’s creative design coming together at Spelman College’s Center for Innovation & The Arts. Following closely behind Turner Construction’s crews, we have completed our solar shades and corrugated Morin panels on one elevation and started the Morin on a second. We have also started installing ACM on the first elevation and nearly completed the insulation that goes under the ACM and Morin on the second. We have reached a similar level of completion on the insulation and ACM within the open, third-story terrace.